12 turbines · under construction · Highland
| Status | Under Construction |
|---|---|
| County / region | Highland |
| Turbines | 12 |
| Installed capacity | 49.9 MW |
| Turbine capacity | 3 MW |
| Tip height | 130 m |
| Operator (or applicant) | Scottish & Southern Energy |
| Turbine manufacturer | not recorded |
| Turbine model | not recorded |
Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.
Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3371.
The application was determined in about 25 months. The register records a refusal in April 2016 before the scheme progressed. Permission was ultimately granted on appeal in April 2017. A planning permission on this site expired in April 2022. That works out at 4.16 MW per turbine on average.
See all wind farms in Highland.