Accolade Wines

1 turbines · operational · Avon

Wind farm facts

StatusOperational
County / regionAvon
Turbines1
Installed capacity2.5 MW
Turbine capacity1.5 MW
Tip height130 m
Operator (or applicant)Clean Earth Energy
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2016 2017 2018 2019 2020 2021 Project timeline Application submitted April 2017 Permission granted September 2017 Under construction February 2019 Operational June 2019 Permission expired September 2020

From application to operation, this scheme took about 2 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 6293.

What the register tells us

The application was determined in about 5 months. Construction to first power took about 4 months. A planning permission on this site expired in September 2020. The scheme has been operating for about 7 years. That works out at 2.5 MW per turbine on average.