1 turbines · operational · Avon
| Status | Operational |
|---|---|
| County / region | Avon |
| Turbines | 1 |
| Installed capacity | 2.5 MW |
| Turbine capacity | 1.5 MW |
| Tip height | 130 m |
| Operator (or applicant) | Clean Earth Energy |
| Turbine manufacturer | not recorded |
| Turbine model | not recorded |
Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.
From application to operation, this scheme took about 2 years.
Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 6293.
The application was determined in about 5 months. Construction to first power took about 4 months. A planning permission on this site expired in September 2020. The scheme has been operating for about 7 years. That works out at 2.5 MW per turbine on average.