Advanced Manufacturing Research Centre

2 turbines · operational · South Yorkshire

Wind farm facts

StatusOperational
County / regionSouth Yorkshire
Turbines2
Installed capacity2.6 MW
Turbine capacity1.3 MW
Tip heightnot recorded
Operator (or applicant)Unknown
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2006 2007 2008 2009 2010 2011 2012 Project timeline Application submitted January 2007 Permission granted June 2007 Operational January 2009 Permission expired June 2011

From application to operation, this scheme took about 2 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3028.

What the register tells us

The application was determined in about 5 months. A planning permission on this site expired in June 2011. The scheme has been operating for about 17 years. That works out at 1.3 MW per turbine on average.