Allt Dearg Wind Farmers LLP

12 turbines · operational · Strathclyde

Wind farm facts

StatusOperational
County / regionStrathclyde
Turbines12
Installed capacity10.8 MW
Turbine capacity0.9 MW
Tip heightnot recorded
Operator (or applicant)Ormsary and Stronachullin Estates (Allt Dearg Wind Farmers LLP)
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2010 2011 2012 2013 Project timeline Application submitted January 2011 Permission granted April 2011 Under construction December 2011 Operational September 2012

From application to operation, this scheme took about 1 year.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3758.

What the register tells us

The application was determined in about 3 months. Construction to first power took about 9 months. The scheme has been operating for about 14 years. That works out at 0.9 MW per turbine on average.