Wind farm facts

StatusOperational
County / regionAvon
Turbines3
Installed capacity6.9 MW
Turbine capacity2.3 MW
Tip height100 m
Operator (or applicant)Ecotricity
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 Project timeline Application submitted June 2008 Permission granted November 2008 Permission expired November 2012 Under construction October 2015 Operational December 2017

From application to operation, this scheme took about 9 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4335.

What the register tells us

The application was determined in about 5 months. Construction to first power took about 26 months. A planning permission on this site expired in November 2012. The scheme has been operating for about 9 years. That works out at 2.3 MW per turbine on average.