Ardoch and Over Enoch Wind Farm (Over Enoch)

2 turbines · operational · Strathclyde

Wind farm facts

StatusOperational
County / regionStrathclyde
Turbines2
Installed capacity4.3 MW
Turbine capacity2.3 MW
Tip height110 m
Operator (or applicant)2020 Renewables/ NTR
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2010 2011 2012 2013 2014 2015 Project timeline Application submitted September 2011 Permission granted April 2012 Under construction November 2013 Operational November 2014

From application to operation, this scheme took about 3 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3855.

What the register tells us

The application was determined in about 7 months. Construction to first power took about 12 months. The scheme has been operating for about 12 years. That works out at 2.15 MW per turbine on average.