60 turbines · operational · Ayrshire
| Status | Operational |
|---|---|
| County / region | Ayrshire |
| Turbines | 60 |
| Installed capacity | 120 MW |
| Turbine capacity | 2 MW |
| Tip height | not recorded |
| Operator (or applicant) | Scottish Power Renewables |
| Turbine manufacturer | not recorded |
| Turbine model | not recorded |
Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.
From application to operation, this scheme took about 5 years.
The register links a second scheme on this site (REPD ref 6798, Under Construction): 13 turbines · 5.6 MW each · 200 m tip height · applicant Scottish Power Renewables. Two schemes on one site usually mean a repowering or an extension — to be confirmed with the operator.
Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3258.
The application was determined in about 26 months. Construction to first power took about 21 months. The scheme has been operating for about 15 years. That works out at 2 MW per turbine on average.