Assel Valley Wind Farm

11 turbines · operational · Strathclyde

Wind farm facts

StatusOperational
County / regionStrathclyde
Turbines11
Installed capacity25 MW
Turbine capacity2.3 MW
Tip heightnot recorded
Operator (or applicant)Falck Renewables
Turbine manufacturerSiemens Gamesa
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2010 2011 2012 2013 2014 2015 2016 2017 Project timeline Application submitted June 2011 Permission expired September 2011 Refused September 2013 Permission granted September 2013 Granted on appeal September 2013 Under construction May 2015 Operational October 2016

From application to operation, this scheme took about 5 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4645.

What the register tells us

The application was determined in about 27 months. Construction to first power took about 17 months. The register records a refusal in September 2013 before the scheme progressed. Permission was ultimately granted on appeal in September 2013. A planning permission on this site expired in September 2011. The scheme has been operating for about 10 years. That works out at 2.27 MW per turbine on average.