Auchadaduie Wind Farm

3 turbines · operational · Strathclyde

Wind farm facts

StatusOperational
County / regionStrathclyde
Turbines3
Installed capacity6.9 MW
Turbine capacity2.3 MW
Tip heightnot recorded
Operator (or applicant)Fyne Futures
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2011 2012 2013 2014 2015 2016 2017 2018 2019 Project timeline Application submitted January 2012 Permission granted July 2014 Permission expired July 2017 Under construction January 2018 Operational November 2018

From application to operation, this scheme took about 6 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4184.

What the register tells us

The application was determined in about 30 months. Construction to first power took about 10 months. A planning permission on this site expired in July 2017. The scheme has been operating for about 8 years. That works out at 2.3 MW per turbine on average.