3 turbines · operational · Strathclyde
| Status | Operational |
|---|---|
| County / region | Strathclyde |
| Turbines | 3 |
| Installed capacity | 6.9 MW |
| Turbine capacity | 2.3 MW |
| Tip height | not recorded |
| Operator (or applicant) | Fyne Futures |
| Turbine manufacturer | not recorded |
| Turbine model | not recorded |
Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.
From application to operation, this scheme took about 6 years.
Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4184.
The application was determined in about 30 months. Construction to first power took about 10 months. A planning permission on this site expired in July 2017. The scheme has been operating for about 8 years. That works out at 2.3 MW per turbine on average.
See all wind farms in Strathclyde.