Avonmouth Port II

2 turbines · operational · Avon

Wind farm facts

StatusOperational
County / regionAvon
Turbines2
Installed capacity5 MW
Turbine capacity2.5 MW
Tip heightnot recorded
Operator (or applicant)Bristol City Council - Energy Management Unit
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2007 2008 2009 2010 2011 2012 2013 2014 Project timeline Application submitted August 2008 Permission granted January 2009 Permission expired January 2010 Under construction April 2013 Operational September 2013

From application to operation, this scheme took about 5 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3927.

What the register tells us

The application was determined in about 5 months. Construction to first power took about 5 months. A planning permission on this site expired in January 2010. The scheme has been operating for about 13 years. That works out at 2.5 MW per turbine on average.