Avonmouth Port

3 turbines · operational · Avon

Wind farm facts

StatusOperational
County / regionAvon
Turbines3
Installed capacity6 MW
Turbine capacity2 MW
Tip heightnot recorded
Operator (or applicant)Bristol Port Authority
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 Original scheme Application submitted August 2005 Permission granted December 2005 Operational August 2007 Later scheme Application submitted May 2010 Permission granted October 2010 Under construction October 2013 Operational April 2014

From application to operation, this scheme took about 2 years.

The register links a second scheme on this site (REPD ref 4159, Operational): 3 turbines · 3 MW each · applicant Bristol Port Company. Two schemes on one site usually mean a repowering or an extension — to be confirmed with the operator.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3194.

What the register tells us

The application was determined in about 4 months. The scheme has been operating for about 19 years. That works out at 2 MW per turbine on average.