Bad a Cheo Wind Farm

13 turbines · operational · Highland

Wind farm facts

StatusOperational
County / regionHighland
Turbines13
Installed capacity26.7 MW
Turbine capacity2.05 MW
Tip height112 m
Operator (or applicant)Innogy
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 Project timeline Application submitted July 2012 Refused September 2013 Permission granted May 2014 Granted on appeal May 2014 Permission expired May 2015 Under construction March 2017 Operational May 2019

From application to operation, this scheme took about 7 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4646.

What the register tells us

The application was determined in about 22 months. Construction to first power took about 26 months. The register records a refusal in September 2013 before the scheme progressed. Permission was ultimately granted on appeal in May 2014. A planning permission on this site expired in May 2015. The scheme has been operating for about 7 years. That works out at 2.05 MW per turbine on average.