Baillie Wind Farm

21 turbines · operational · Highland

Wind farm facts

StatusOperational
County / regionHighland
Turbines21
Installed capacity52.5 MW
Turbine capacity2.5 MW
Tip heightnot recorded
Operator (or applicant)Baillie Windfarm Ltd
Turbine manufacturerNordex
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 Project timeline Application submitted July 2004 Permission granted January 2010 Under construction July 2011 Operational March 2013 Permission expired January 2015

From application to operation, this scheme took about 9 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4021.

What the register tells us

The application was determined in about 66 months. Construction to first power took about 20 months. A planning permission on this site expired in January 2015. The scheme has been operating for about 13 years. That works out at 2.5 MW per turbine on average.