Ballymena Wind Park Limited

2 turbines · operational · Co. Antrim

Wind farm facts

StatusOperational
County / regionCo. Antrim
Turbines2
Installed capacity4.7 MW
Turbine capacity2.35 MW
Tip heightnot recorded
Operator (or applicant)White Young Green Planning
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2008 2009 2010 2011 2012 2013 2014 2015 Project timeline Application submitted July 2009 Permission granted April 2010 Operational January 2013 Permission expired April 2014

From application to operation, this scheme took about 4 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 2866.

What the register tells us

The application was determined in about 9 months. A planning permission on this site expired in April 2014. The scheme has been operating for about 13 years. That works out at 2.35 MW per turbine on average.