♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 Project timeline Application submitted May 2005 Permission granted September 2005 Operational November 2006 Permission expired September 2014

From application to operation, this scheme took about 1 year.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 2715.

What the register tells us

The application was determined in about 4 months. A planning permission on this site expired in September 2014. The scheme has been operating for about 20 years. At that age, wind farms commonly become candidates for repowering or life extension — nothing in the register confirms such a plan here. That works out at 0.77 MW per turbine on average.