Bankend Rig

11 turbines · operational · Strathclyde

Wind farm facts

StatusOperational
County / regionStrathclyde
Turbines11
Installed capacity14.3 MW
Turbine capacity1.3 MW
Tip heightnot recorded
Operator (or applicant)I & H Brown Ltd
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 Project timeline Permission expired June 2003 Application submitted June 2006 Permission granted June 2011 Under construction January 2012 Operational March 2013

From application to operation, this scheme took about 7 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4055.

What the register tells us

The application was determined in about 60 months. Construction to first power took about 14 months. A planning permission on this site expired in June 2003. The scheme has been operating for about 13 years. That works out at 1.3 MW per turbine on average.