9 turbines · operational · Devon
| Status | Operational |
|---|---|
| County / region | Devon |
| Turbines | 9 |
| Installed capacity | 18 MW |
| Turbine capacity | 2 MW |
| Tip height | 103 m |
| Operator (or applicant) | Blackrock Real Assets |
| Turbine manufacturer | not recorded |
| Turbine model | not recorded |
Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.
From application to operation, this scheme took about 10 years.
Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4057.
The application was determined in about 71 months. Construction to first power took about 3 months. The register records a refusal in July 2011 before the scheme progressed. Permission was ultimately granted on appeal in October 2012. The scheme has been operating for about 10 years. That works out at 2 MW per turbine on average.
See all wind farms in Devon.