Batsworthy Cross

9 turbines · operational · Devon

Wind farm facts

StatusOperational
County / regionDevon
Turbines9
Installed capacity18 MW
Turbine capacity2 MW
Tip height103 m
Operator (or applicant)Blackrock Real Assets
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 Project timeline Application submitted November 2006 Refused July 2011 Permission granted October 2012 Granted on appeal October 2012 Under construction January 2016 Operational April 2016

From application to operation, this scheme took about 10 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4057.

What the register tells us

The application was determined in about 71 months. Construction to first power took about 3 months. The register records a refusal in July 2011 before the scheme progressed. Permission was ultimately granted on appeal in October 2012. The scheme has been operating for about 10 years. That works out at 2 MW per turbine on average.