🌬️ Onshore wind farm

Batsworthy Cross
Devon

Recorded in WhichWindTurbine: 9 wind turbines in operation. Point the app at one of them to see its profile in real time.

9
turbines
18 MW
MW total
2 MW
per turbine
103 m
tip height

📍 9 turbines mapped — each dot is a turbine recorded in the database. Average position: 50.97631 N · 3.68389 W.

Batsworthy Cross

9 turbines · operational · Devon

Wind farm facts

StatusOperational
County / regionDevon
Turbines9
Installed capacity18 MW
Turbine capacity2 MW
Tip height103 m
Operator (or applicant)Blackrock Real Assets
Turbine manufacturernot recorded
Turbine modelnot recorded
Open this wind farm in WhichWindTurbine Interactive map + augmented-reality identification on site

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

→ ~20382010201520202025today123456
  1. 1Nov 2006 — Application submitted
  2. 2Jul 2011 — Refused
  3. 3Oct 2012 — Permission granted
  4. 4Oct 2012 — Granted on appeal
  5. 5Jan 2016 — Under construction
  6. 6Apr 2016 — Operational

DevelopmentConstructionOperationAhead (repowering horizon at 22 years)

From application to operation, this scheme took about 10 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4057.

What the register tells us

The application was determined in about 71 months. Construction to first power took about 3 months. The register records a refusal in July 2011 before the scheme progressed. Permission was ultimately granted on appeal in October 2012. The scheme has been operating for about 10 years. That works out at 2 MW per turbine on average.

Nearby

See all wind farms in Devon.

Sources and dates

DataSourceExtract
Site, capacity, status, planning milestonesRenewable Energy Planning Database (DESNZ, Open Government Licence v3)Q2 2026, published 03/08/2026
Turbine positionsOpenStreetMap contributors (ODbL)19/08/2026
Manufacturer and modelOpenStreetMap tags, unverified — REPD does not record turbine models. Known for 41 % of UK turbines (manufacturer) and 32 % (model); some values are propagated within a site and may be wrong.19/08/2026

Public data may lag behind operator figures. Spotted an error? Suggest a correction from the app.