9 turbines · revised · Cumbria
| Status | Revised |
|---|---|
| County / region | Cumbria |
| Turbines | 9 |
| Installed capacity | 18 MW |
| Turbine capacity | 2 MW |
| Tip height | not recorded |
| Operator (or applicant) | EDF Energy |
| Turbine manufacturer | not recorded |
| Turbine model | not recorded |
Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.
The register links a second scheme on this site (REPD ref 4544, Operational): 9 turbines · 3.45 MW each · applicant EDF Energy Renewables. Two schemes on one site usually mean a repowering or an extension — to be confirmed with the operator.
Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3777.
The register records a refusal in December 2011 before the scheme progressed. That works out at 2 MW per turbine on average.