Beinn an Tuirc Phase 2

19 turbines · operational · Strathclyde

Wind farm facts

StatusOperational
County / regionStrathclyde
Turbines19
Installed capacity43.7 MW
Turbine capacity2.3 MW
Tip heightnot recorded
Operator (or applicant)Scottish Power Renewables
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 Project timeline Application submitted July 2005 Permission granted July 2007 Under construction April 2010 Operational September 2014

From application to operation, this scheme took about 9 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4525.

What the register tells us

The application was determined in about 24 months. Construction to first power took about 53 months. The scheme has been operating for about 12 years. That works out at 2.3 MW per turbine on average.

Nearby

See all wind farms in Strathclyde.