Beinn Tharsuinn Windfarm Project

17 turbines · operational · Highland

Wind farm facts

StatusOperational
County / regionHighland
Turbines17
Installed capacity29.8 MW
Turbine capacity1.75 MW
Tip heightnot recorded
Operator (or applicant)CRE Energy/ Scottish Power
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2001 2002 2003 2004 2005 2006 Project timeline Application submitted April 2002 Permission granted February 2005 Under construction May 2005 Operational December 2005

From application to operation, this scheme took about 3 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4669.

What the register tells us

The application was determined in about 34 months. Construction to first power took about 7 months. The scheme has been operating for about 21 years. At that age, wind farms commonly become candidates for repowering or life extension — nothing in the register confirms such a plan here. That works out at 1.75 MW per turbine on average.