Bendealt Wind Farm, Highland

18 turbines · operational · Highland

Wind farm facts

StatusOperational
County / regionHighland
Turbines18
Installed capacity9 MW
Turbine capacity0.5 MW
Tip heightnot recorded
Operator (or applicant)RWE npower
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

1994 1997 2000 2003 2006 2009 2012 2015 2018 Project timeline Application submitted May 1995 Permission granted August 1996 Operational September 1997 Permission expired August 2017

From application to operation, this scheme took about 2 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3296.

What the register tells us

The application was determined in about 15 months. A planning permission on this site expired in August 2017. The scheme has been operating for about 29 years. At that age, wind farms commonly become candidates for repowering or life extension — nothing in the register confirms such a plan here. That works out at 0.5 MW per turbine on average.