♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 Project timeline Application submitted October 2006 Refused May 2007 Permission granted February 2008 Granted on appeal February 2008 Under construction October 2012 Operational March 2013 Permission expired February 2015

From application to operation, this scheme took about 7 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3947.

What the register tells us

The application was determined in about 16 months. Construction to first power took about 5 months. The register records a refusal in May 2007 before the scheme progressed. Permission was ultimately granted on appeal in February 2008. A planning permission on this site expired in February 2015. The scheme has been operating for about 13 years. That works out at 2.3 MW per turbine on average.