1 turbines · operational · Northumberland
| Status | Operational |
|---|---|
| County / region | Northumberland |
| Turbines | 1 |
| Installed capacity | 2.3 MW |
| Turbine capacity | 2.3 MW |
| Tip height | not recorded |
| Operator (or applicant) | Harworth Power |
| Turbine manufacturer | not recorded |
| Turbine model | not recorded |
Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.
From application to operation, this scheme took about 7 years.
Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3947.
The application was determined in about 16 months. Construction to first power took about 5 months. The register records a refusal in May 2007 before the scheme progressed. Permission was ultimately granted on appeal in February 2008. A planning permission on this site expired in February 2015. The scheme has been operating for about 13 years. That works out at 2.3 MW per turbine on average.