Bin Mountain

6 turbines · operational · Co. Tyrone

Wind farm facts

StatusOperational
County / regionCo. Tyrone
Turbines6
Installed capacity9 MW
Turbine capacity1.5 MW
Tip heightnot recorded
Operator (or applicant)Greencoat UK Wind
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2000 2002 2004 2006 2008 2010 2012 2014 2016 2018 2020 Project timeline Application submitted May 2001 Permission granted February 2006 Under construction December 2006 Operational February 2007 Permission expired February 2019

From application to operation, this scheme took about 6 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3113.

What the register tells us

The application was determined in about 57 months. Construction to first power took about 2 months. A planning permission on this site expired in February 2019. The scheme has been operating for about 19 years. That works out at 1.5 MW per turbine on average.