Bishopthorpe

8 turbines · operational · Lincolnshire

Wind farm facts

StatusOperational
County / regionLincolnshire
Turbines8
Installed capacity16.4 MW
Turbine capacity2 MW
Tip height115 m
Operator (or applicant)Greencoat UK (formerly BayWa r.e.)
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2011 2012 2013 2014 2015 2016 2017 2018 2019 Project timeline Application submitted October 2012 Refused February 2014 Permission granted March 2015 Under construction January 2016 Operational January 2017 Permission expired March 2018

From application to operation, this scheme took about 5 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4256.

What the register tells us

The application was determined in about 29 months. Construction to first power took about 12 months. The register records a refusal in February 2014 before the scheme progressed. A planning permission on this site expired in March 2018. The scheme has been operating for about 9 years. That works out at 2.05 MW per turbine on average.