Bloodhills - repowering

2 turbines · operational · Norfolk

Wind farm facts

StatusOperational
County / regionNorfolk
Turbines2
Installed capacity1 MW
Turbine capacity0.5 MW
Tip heightnot recorded
Operator (or applicant)The Farm Energy Partnership LLP
Turbine manufacturernot recorded
Turbine modelTurbowind T400

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2011 2012 2013 2014 2015 2016 Project timeline Permission expired May 2012 Application submitted February 2013 Permission granted May 2013 Under construction July 2014 Operational June 2015

From application to operation, this scheme took about 2 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3924.

What the register tells us

The application was determined in about 3 months. Construction to first power took about 11 months. A planning permission on this site expired in May 2012. The scheme has been operating for about 11 years. That works out at 0.5 MW per turbine on average.