Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.
From application to operation, this scheme took about 5 years.
Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4663.
The application was determined in about 12 months. Construction to first power took about 15 months. A planning permission on this site expired in July 2016. The scheme has been operating for about 14 years. That works out at 3.4 MW per turbine on average.