Blyth Harbour Wind Farm (re-power)

1 turbines · operational · Northumberland

Wind farm facts

StatusOperational
County / regionNorthumberland
Turbines1
Installed capacity3.4 MW
Turbine capacity3.4 MW
Tip heightnot recorded
Operator (or applicant)Hainsford Energy
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 Project timeline Application submitted July 2007 Permission granted July 2008 Under construction June 2011 Operational September 2012 Permission expired July 2016

From application to operation, this scheme took about 5 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4663.

What the register tells us

The application was determined in about 12 months. Construction to first power took about 15 months. A planning permission on this site expired in July 2016. The scheme has been operating for about 14 years. That works out at 3.4 MW per turbine on average.