Blyth Harbour Wind Farm

9 turbines · operational · Northumberland

Wind farm facts

StatusOperational
County / regionNorthumberland
Turbines9
Installed capacity2.7 MW
Turbine capacity0.3 MW
Tip heightnot recorded
Operator (or applicant)Border Wind Farms Ltd
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

1990 1991 1992 1993 Project timeline Application submitted May 1991 Permission granted March 1992 Operational December 1992

From application to operation, this scheme took about 1 year.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3659.

What the register tells us

The application was determined in about 10 months. The scheme has been operating for about 34 years. At that age, wind farms commonly become candidates for repowering or life extension — nothing in the register confirms such a plan here. That works out at 0.3 MW per turbine on average.