Boddington Reservoir

1 turbines · operational · Northamptonshire

Wind farm facts

StatusOperational
County / regionNorthamptonshire
Turbines1
Installed capacity1.5 MW
Turbine capacity1.5 MW
Tip heightnot recorded
Operator (or applicant)Unknown
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2010 2011 2012 2013 2014 2015 2016 2017 2018 Project timeline Application submitted March 2011 Permission granted December 2011 Under construction August 2013 Operational April 2014 Permission expired December 2017

From application to operation, this scheme took about 3 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3732.

What the register tells us

The application was determined in about 9 months. Construction to first power took about 8 months. A planning permission on this site expired in December 2017. The scheme has been operating for about 12 years. That works out at 1.5 MW per turbine on average.

Nearby

See all wind farms in Northamptonshire.