🌬️ Onshore wind farm

Bodtegir
Clwyd

Recorded in WhichWindTurbine: 1 wind turbine in operation. Point the app at one of them to see its profile in real time.

1
turbines
1.5 MW
MW total
1.5 MW
per turbine
100 m
tip height

📍 1 turbine mapped — each dot is a turbine recorded in the database. Average position: 53.0173 N · 3.49922 W.

Bodtegir

1 turbines · operational · Clwyd

Wind farm facts

StatusOperational
County / regionClwyd
Turbines1
Installed capacity1.5 MW
Turbine capacity1.5 MW
Tip height100 m
Operator (or applicant)Clean Earth Energy
Turbine manufacturernot recorded
Turbine modelnot recorded
Open this wind farm in WhichWindTurbine Interactive map + augmented-reality identification on site

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

→ ~2040201620182020202220242026today1234
  1. 1Feb 2016 — Application submitted
  2. 2Apr 2016 — Permission granted
  3. 3Jun 2017 — Under construction
  4. 4Nov 2017 — Operational

The register also records a planning permission expiry in Apr 2021, after construction had started: an administrative date with no effect on the wind farm, left off the axis.

DevelopmentConstructionOperationAhead (repowering horizon at 22 years)

From application to operation, this scheme took about 1 year.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 6033.

What the register tells us

The application was determined in about 2 months. Construction to first power took about 5 months. A planning permission on this site expired in April 2021. The scheme has been operating for about 9 years. That works out at 1.5 MW per turbine on average.

Sources and dates

DataSourceExtract
Site, capacity, status, planning milestonesRenewable Energy Planning Database (DESNZ, Open Government Licence v3)Q2 2026, published 03/08/2026
Turbine positionsOpenStreetMap contributors (ODbL)19/08/2026
Manufacturer and modelOpenStreetMap tags, unverified — REPD does not record turbine models. Known for 41 % of UK turbines (manufacturer) and 32 % (model); some values are propagated within a site and may be wrong.19/08/2026

Public data may lag behind operator figures. Spotted an error? Suggest a correction from the app.