Bodtegir

1 turbines · operational · Clwyd

Wind farm facts

StatusOperational
County / regionClwyd
Turbines1
Installed capacity1.5 MW
Turbine capacity1.5 MW
Tip height100 m
Operator (or applicant)Clean Earth Energy
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2015 2016 2017 2018 2019 2020 2021 2022 Project timeline Application submitted February 2016 Permission granted April 2016 Under construction June 2017 Operational November 2017 Permission expired April 2021

From application to operation, this scheme took about 1 year.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 6033.

What the register tells us

The application was determined in about 2 months. Construction to first power took about 5 months. A planning permission on this site expired in April 2021. The scheme has been operating for about 9 years. That works out at 1.5 MW per turbine on average.