Bogenlea Farm

1 turbines · operational · Grampian

Wind farm facts

StatusOperational
County / regionGrampian
Turbines1
Installed capacity2.3 MW
Turbine capacity2.3 MW
Tip heightnot recorded
Operator (or applicant)Eco2
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2008 2009 2010 2011 2012 2013 2014 2015 Project timeline Application submitted May 2009 Permission granted December 2009 Permission expired December 2010 Under construction October 2013 Operational August 2014

From application to operation, this scheme took about 5 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4346.

What the register tells us

The application was determined in about 7 months. Construction to first power took about 10 months. A planning permission on this site expired in December 2010. The scheme has been operating for about 12 years. That works out at 2.3 MW per turbine on average.