Bonerbo Wind Turbines

3 turbines · operational · Fife

Wind farm facts

StatusOperational
County / regionFife
Turbines3
Installed capacity1.5 MW
Turbine capacity0.5 MW
Tip heightnot recorded
Operator (or applicant)Messrs Stevenson, Watson and Brunton
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2010 2011 2012 2013 2014 2015 Scheme REPD 3370 Permission expired May 2011 Application submitted July 2012 Permission granted May 2013 Under construction February 2014 Operational December 2014 Scheme REPD 3847 Application submitted February 2012

From application to operation, this scheme took about 2 years.

The register links a second scheme on this site (REPD ref 3847, Revised): 3 turbines · 0.9 MW each · applicant Messrs Stevenson, Watson and Brunton. Two schemes on one site usually mean a repowering or an extension — to be confirmed with the operator.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3370.

What the register tells us

The application was determined in about 10 months. Construction to first power took about 10 months. A planning permission on this site expired in May 2011. The scheme has been operating for about 12 years. That works out at 0.5 MW per turbine on average.