Boundary Lane

3 turbines · operational · County Durham

Wind farm facts

StatusOperational
County / regionCounty Durham
Turbines3
Installed capacity6 MW
Turbine capacity2 MW
Tip heightnot recorded
Operator (or applicant)EDF
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 Project timeline Application submitted June 2009 Permission granted February 2011 Under construction September 2012 Operational March 2013 Permission expired February 2016

From application to operation, this scheme took about 4 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3674.

What the register tells us

The application was determined in about 20 months. Construction to first power took about 6 months. A planning permission on this site expired in February 2016. The scheme has been operating for about 13 years. That works out at 2 MW per turbine on average.

Nearby