24 turbines · operational · Borders
| Status | Operational |
|---|---|
| County / region | Borders |
| Turbines | 24 |
| Installed capacity | 31.2 MW |
| Turbine capacity | 1.3 MW |
| Tip height | 80 m |
| Operator (or applicant) | PowerGen and Natural Power |
| Turbine manufacturer | not recorded |
| Turbine model | not recorded |
Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.
From application to operation, this scheme took about 2 years.
Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3299.
The application was determined in about 5 months. The scheme has been operating for about 24 years. At that age, wind farms commonly become candidates for repowering or life extension — nothing in the register confirms such a plan here. That works out at 1.3 MW per turbine on average.