Boyndie Airfield Extension

8 turbines · operational · Grampian

Wind farm facts

StatusOperational
County / regionGrampian
Turbines8
Installed capacity16.7 MW
Turbine capacity2 MW
Tip heightnot recorded
Operator (or applicant)RDC Scotland Ltd/ Falck Renewables
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 Original scheme Application submitted June 2003 Permission granted July 2004 Under construction September 2005 Operational February 2006 Later scheme Application submitted August 2008 Permission granted August 2009 Operational January 2010 Refused May 2016

From application to operation, this scheme took about 3 years.

The register links a second scheme on this site (REPD ref 2691, Operational): 1 turbines · 2.3 MW each · applicant Boyndie Wind Farm. Two schemes on one site usually mean a repowering or an extension — to be confirmed with the operator.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4671.

What the register tells us

The application was determined in about 13 months. Construction to first power took about 5 months. The scheme has been operating for about 20 years. At that age, wind farms commonly become candidates for repowering or life extension — nothing in the register confirms such a plan here. That works out at 2.09 MW per turbine on average.