10 turbines · operational · Essex
| Status | Operational |
|---|---|
| County / region | Essex |
| Turbines | 10 |
| Installed capacity | 20 MW |
| Turbine capacity | 2 MW |
| Tip height | not recorded |
| Operator (or applicant) | Npower Renewables |
| Turbine manufacturer | Senvion |
| Turbine model | not recorded |
Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.
From application to operation, this scheme took about 7 years.
Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3936.
The application was determined in about 4 months. Construction to first power took about 17 months. A planning permission on this site expired in July 2010. The scheme has been operating for about 13 years. That works out at 2 MW per turbine on average.