🌬️ Onshore wind farm

Brockholes Wind Cluster
Borders

Recorded in WhichWindTurbine: 3 wind turbines in operation. Point the app at one of them to see its profile in real time.

3
turbines
2.4 MW
MW total
0.8 MW
per turbine

📍 3 turbines mapped — each dot is a turbine recorded in the database. Average position: 55.86302 N · 2.29315 W.

Brockholes Wind Cluster

3 turbines · operational · Borders

Wind farm facts

StatusOperational
County / regionBorders
Turbines3
Installed capacity2.4 MW
Turbine capacity0.8 MW
Tip heightnot recorded
Operator (or applicant)Brockholes Farm
Turbine manufacturernot recorded
Turbine modelnot recorded
Open this wind farm in WhichWindTurbine Interactive map + augmented-reality identification on site

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

→ ~20352010201520202025today1234
  1. 1Apr 2009 — Application submitted
  2. 2May 2010 — Permission granted
  3. 3Feb 2012 — Under construction
  4. 4Feb 2013 — Operational

The register also records a planning permission expiry in May 2014, after construction had started: an administrative date with no effect on the wind farm, left off the axis.

DevelopmentConstructionOperationAhead (repowering horizon at 22 years)

From application to operation, this scheme took about 4 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 2672.

What the register tells us

The application was determined in about 13 months. Construction to first power took about 12 months. A planning permission on this site expired in May 2014. The scheme has been operating for about 13 years. That works out at 0.8 MW per turbine on average.

Nearby

See all wind farms in Borders.

Sources and dates

DataSourceExtract
Site, capacity, status, planning milestonesRenewable Energy Planning Database (DESNZ, Open Government Licence v3)Q2 2026, published 03/08/2026
Turbine positionsOpenStreetMap contributors (ODbL)19/08/2026
Manufacturer and modelOpenStreetMap tags, unverified — REPD does not record turbine models. Known for 41 % of UK turbines (manufacturer) and 32 % (model); some values are propagated within a site and may be wrong.19/08/2026

Public data may lag behind operator figures. Spotted an error? Suggest a correction from the app.