10 turbines · operational · Lanarkshire
| Status | Operational |
|---|---|
| County / region | Lanarkshire |
| Turbines | 10 |
| Installed capacity | 48 MW |
| Turbine capacity | not recorded |
| Tip height | 149.9 m |
| Operator (or applicant) | BayWa r.e. UK Limited |
| Turbine manufacturer | Nordex |
| Turbine model | N133 |
Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.
From application to operation, this scheme took about 5 years.
Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 6708.
The application was determined in about 6 months. Construction to first power took about 15 months. A planning permission on this site expired in April 2024. The scheme has been operating for about 2 years. That works out at 4.8 MW per turbine on average.
See all wind farms in Lanarkshire.