Brotherton (formerly Paul Matthew Hill wind turbines)

2 turbines · operational · Grampian

Wind farm facts

StatusOperational
County / regionGrampian
Turbines2
Installed capacity4.6 MW
Turbine capacity2.3 MW
Tip heightnot recorded
Operator (or applicant)Renewable Energy Ventures
Turbine manufacturerEnercon
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2012 2013 2014 2015 2016 2017 2018 Project timeline Application submitted April 2013 Refused February 2014 Permission granted July 2014 Granted on appeal July 2014 Under construction December 2016 Operational May 2017

From application to operation, this scheme took about 4 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4411.

What the register tells us

The application was determined in about 15 months. Construction to first power took about 5 months. The register records a refusal in February 2014 before the scheme progressed. Permission was ultimately granted on appeal in July 2014. The scheme has been operating for about 9 years. That works out at 2.3 MW per turbine on average.