BROWNIELEYS - 3 WIND TURBINES

3 turbines · operational · Grampian

Wind farm facts

StatusOperational
County / regionGrampian
Turbines3
Installed capacity7.5 MW
Turbine capacity2.35 MW
Tip heightnot recorded
Operator (or applicant)Brownieleys Renewables/Muirden Energy
Turbine manufacturerEnercon
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2011 2012 2013 2014 2015 2016 2017 2018 Project timeline Application submitted April 2012 Refused April 2013 Permission granted October 2013 Granted on appeal October 2013 Under construction July 2016 Operational February 2017

From application to operation, this scheme took about 5 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4348.

What the register tells us

The application was determined in about 18 months. Construction to first power took about 7 months. The register records a refusal in April 2013 before the scheme progressed. Permission was ultimately granted on appeal in October 2013. The scheme has been operating for about 9 years. That works out at 2.5 MW per turbine on average.