Burnfoot East Wind Farm (further extension)

3 turbines · operational · Clackmannanshire

Wind farm facts

StatusOperational
County / regionClackmannanshire
Turbines3
Installed capacity10.8 MW
Turbine capacity3.6 MW
Tip height135 m
Operator (or applicant)Wind Prospect Developments
Turbine manufacturerVestas
Turbine modelV112

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2016 2017 2018 2019 2020 2021 Project timeline Application submitted January 2017 Permission granted March 2019 Under construction September 2019 Operational July 2020

From application to operation, this scheme took about 3 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 6324.

What the register tells us

The application was determined in about 26 months. Construction to first power took about 10 months. The scheme has been operating for about 6 years. That works out at 3.6 MW per turbine on average.