Burnfoot Hill

13 turbines · operational · Clackmannanshire

Wind farm facts

StatusOperational
County / regionClackmannanshire
Turbines13
Installed capacity26 MW
Turbine capacity2 MW
Tip heightnot recorded
Operator (or applicant)EDF Energies Nouvelles
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2005 2006 2007 2008 2009 2010 2011 Project timeline Application submitted March 2006 Permission granted March 2007 Under construction August 2010 Operational October 2010

From application to operation, this scheme took about 4 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 2902.

What the register tells us

The application was determined in about 12 months. Construction to first power took about 2 months. The scheme has been operating for about 16 years. That works out at 2 MW per turbine on average.