Burnt House Farm

3 turbines · operational · Cambridgeshire

Wind farm facts

StatusOperational
County / regionCambridgeshire
Turbines3
Installed capacity6 MW
Turbine capacity2 MW
Tip heightnot recorded
Operator (or applicant)Fivestone Ltd
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2008 2009 2010 2011 2012 2013 2014 Project timeline Application submitted June 2009 Refused January 2010 Permission expired July 2010 Permission granted July 2011 Granted on appeal July 2011 Under construction January 2013 Operational June 2013

From application to operation, this scheme took about 4 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3686.

What the register tells us

The application was determined in about 25 months. Construction to first power took about 5 months. The register records a refusal in January 2010 before the scheme progressed. Permission was ultimately granted on appeal in July 2011. A planning permission on this site expired in July 2010. The scheme has been operating for about 13 years. That works out at 2 MW per turbine on average.