Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2007 2008 2009 2010 2011 2012 2013 2014 2015 Project timeline Application submitted May 2008 Permission granted September 2009 Permission expired September 2011 Under construction July 2013 Operational January 2014

From application to operation, this scheme took about 6 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3992.

What the register tells us

The application was determined in about 16 months. Construction to first power took about 6 months. A planning permission on this site expired in September 2011. The scheme has been operating for about 12 years. That works out at 3.4 MW per turbine on average.