Burton Wold Wind Farm South

3 turbines · operational · Northamptonshire

Wind farm facts

StatusOperational
County / regionNorthamptonshire
Turbines3
Installed capacity7.5 MW
Turbine capacity2.75 MW
Tip height137 m
Operator (or applicant)Infinergy/ Muirhall Energy
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2014 2015 2016 2017 2018 Project timeline Application submitted February 2015 Permission granted March 2015 Under construction September 2016 Operational April 2017

From application to operation, this scheme took about 2 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 5277.

What the register tells us

The application was determined in about 1 month. Construction to first power took about 7 months. The scheme has been operating for about 9 years. That works out at 2.5 MW per turbine on average.