10 turbines · operational · Northamptonshire
| Status | Operational |
|---|---|
| County / region | Northamptonshire |
| Turbines | 10 |
| Installed capacity | 20 MW |
| Turbine capacity | 2 MW |
| Tip height | not recorded |
| Operator (or applicant) | Gravis Capital Management |
| Turbine manufacturer | not recorded |
| Turbine model | not recorded |
Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.
From application to operation, this scheme took about 2 years.
The register links a second scheme on this site (REPD ref 3973, Revised): 7 turbines · 2.3 MW each · applicant Burton Wold Wind Farm Extension Ltd. Two schemes on one site usually mean a repowering or an extension — to be confirmed with the operator.
Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4672.
The application was determined in about 0 month. Construction to first power took about 4 months. The scheme has been operating for about 20 years. At that age, wind farms commonly become candidates for repowering or life extension — nothing in the register confirms such a plan here. That works out at 2 MW per turbine on average.
See all wind farms in Northamptonshire.