10 turbines · operational · Highland
| Status | Operational |
|---|---|
| County / region | Highland |
| Turbines | 10 |
| Installed capacity | 36 MW |
| Turbine capacity | 3.6 MW |
| Tip height | 127 m |
| Operator (or applicant) | E.ON UK |
| Turbine manufacturer | Vestas |
| Turbine model | V112 |
Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.
From application to operation, this scheme took about 7 years.
Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4351.
The application was determined in about 23 months. Construction to first power took about 30 months. The register records a refusal in January 2021 before the scheme progressed. Permission was ultimately granted on appeal in July 2021. A planning permission on this site expired in July 2026. The scheme has been operating for about 0 year. That works out at 3.6 MW per turbine on average.