Camster II

10 turbines · operational · Highland

Wind farm facts

StatusOperational
County / regionHighland
Turbines10
Installed capacity36 MW
Turbine capacity3.6 MW
Tip height127 m
Operator (or applicant)E.ON UK
Turbine manufacturerVestas
Turbine modelV112

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 Project timeline Application submitted August 2019 Refused January 2021 Permission granted July 2021 Granted on appeal July 2021 Under construction October 2023 Operational April 2026 Permission expired July 2026

From application to operation, this scheme took about 7 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4351.

What the register tells us

The application was determined in about 23 months. Construction to first power took about 30 months. The register records a refusal in January 2021 before the scheme progressed. Permission was ultimately granted on appeal in July 2021. A planning permission on this site expired in July 2026. The scheme has been operating for about 0 year. That works out at 3.6 MW per turbine on average.